# Activate Your Enphase IQ Combiner

June 12, 2026

## STEP 3: Turn on IQ combiner breakers

- Your Enphase IQ Combiner may be located next to your electrical panel, your meter, or your AC disconnect. Look for a small grey box labeled "Enphase."

**Note**: If you instead see a white box labeled "SolarEdge," click **[here](https://help.palmetto.com/en/articles/9948730-activate-your-solaredge-inverter)** for step 3 instructions.

- Inside the IQ Combiner box, flip all breakers to the center. There may be two (2) to five **5** breakers in this box.

- The inverter may take a while to turn on, depending on the time of day. When the IQ Combiner/Envoy has connected successfully, the left-most LED light will be solid green.

**Note**: If none of the LEDs are lit, it is not powered on. Turn off and on the breaker and/or disconnect switch feeding the IQ Combiner. If the IQ Combiner fails to power up, contact Palmetto for assistance.

## After you activate your solar energy system

The green lights indicate that your system is active but it takes a few days to confirm. If activation was successful, we'll know in 1-3 days when performance data begins to appear.